Corrected EGT
—°C
Power assurance test — target N1 and Step-17 corrected limit check.
—°C
—%
—lb/Hr
AMP BD500-A-J71-00-00-01AAA-320B-A, Issue 021 (2025-10-14) — Power plant: Operation test (Power assurance test). Corrections per Step 17 (altitude, N1-setting error, nacelle anti-ice). Limits from Table 8 at recorded OAT. N1 is the target set, not a checked limit.
| OAT °C | N1 target | N2 % | EGT °C | Wf lb/Hr | Wf kg/Hr |
|---|